by ceegsproject | Jun 18, 2024 | CEEGS Facility HZDR, News
The recently delivered CO2 pump was installed and connected to the CEEGS test facility at the Helmholtz-Zentrum Dresden Rossendorf (HZDR). Subsequently, pressure and leakage tests were performed to ensure the safe and stable operation of the pump. Once the electrical...
by ceegsproject | Apr 8, 2024 | CEEGS Facility HZDR, News
Our researchers at the Helmholtz-Zentrum Dresden Rossendorf (HZDR) successfully completed a pressure test for high temperature and pressure, marking a significant milestone for our operations. With the recent delivery of the CO2 pump, the CEEGS facility can now...
by ceegsproject | Mar 8, 2024 | CEEGS Facility HZDR, News
As you might have read in previous posts, the Helmholtz Centre Dresden Rossendorf (HZDR) is installing an experimental facility at its premises to prove the CEEGS cycle at the laboratory scale. This week, the CO2 pump for the CEEGS facility was delivered to HZDR. The...
by ceegsproject | Feb 5, 2024 | CEEGS Facility HZDR, News
As reported in previous posts, the Helmholtz Centre Dresden Rossendorf (HZDR) is installing an experimental facility at its premises to prove the CEEGS cycle at the laboratory scale. At the outset of 2024, the first post-commissioning operations were conducted at the...
by ceegsproject | Jan 15, 2024 | CEEGS Facility HZDR, News
As reported last autumn, the Helmholtz Centre Dresden Rossendorf (HZDR) is installing an experimental facility at its premises to prove the CEEGS cycle at the laboratory scale. To operate a thermo-fluid dynamic facility at high pressure, certain safety measures need...
by ceegsproject | Nov 6, 2023 | CEEGS Facility HZDR, News
Earlier this autumn, the two main heat exchangers HXW and HXI of the experimental facility at the Helmholtz Centre Dresden Rossendorf (HZDR) were installed. The design, assembling, and operation of the facility is part of the work package 5 and shall prove the CEEGS...